Renewable Energy and Net Metering
Gulf Power customers who install a renewable energy system (up to 2 MW) at their home or business, may qualify for interconnection to the Gulf Power system. Gulf Power will meter the system and provide credits for any excess electricity through a process called net metering.
Links to the application and agreements, as well as helpful information, are below.
How do I apply for interconnection and net metering?
After your renewable generation is installed AND inspected by the local code official the following process occurs:
- Complete and forward a Standard Interconnection Application for Customer-Owned Renewable Generation(Application) and required documentation (detailed in application) to Gulf Power at the following address:
- Gulf Power Company
Attn: Mass Market Renewable Analyst, Bin 231
One Energy Place
Pensacola, Florida 32520-0231
- Gulf Power will review your Application and documentation, then Gulf Power will forward the appropriate Standard Interconnection Agreement for Customer-Owned Renewable Generation (Agreement) to you, depending on the size on your installation.
- Sign and return the Agreement to Gulf Power at the address above.
- Gulf Power will schedule and conduct an on-site inspection.
- Upon successful inspection, Gulf Power will install the appropriate net metering equipment.
- Gulf Power will notify you of authorization to interconnect your renewable energy system to our grid.
Standard Interconnection Application for Customer-Owned Renewable Generation Systems
Tier 1 Standard Interconnection Agreement for Customer-Owned Tier 1 Renewable Generation Systems (10 kW or less)
Tier 2 Standard Interconnection Agreement for Customer-Owned Tier 2 Renewable Generation Systems (Greater than 10 kW and Less than or Equal to 100 kW)
Tier 3 Standard Interconnection Agreement for Customer-Owned Tier 3 Renewable Generation Systems (Greater than 100 kW and Less than or Equal to 2 MW)
Still Have Questions...Contact Our Renewable Specialist at 850.444.6369.